Upload an 8,760-hour demand profile (template below) or enter a 24×12 hour-by-month matrix. An uploaded profile takes precedence.
Using 24×12 matrix (default C&I shape, 30 MW peak).
Generation profiles (8,760-hr, normalized 0–1)
Bundled default (CUF 19.6%).
Bundled default (CUF 36.3%).
Target return ▶
%
%
yrs
yrs
% of PPA tariff
%/yr
Compounds the grid (baseline) tariff each year beyond the last published MSEDCL schedule (FY2029-30). Raises later-year customer savings; the RE tariff and developer economics are unaffected. Default 0 = grid held flat (conservative).
Maharashtra grid tariff (MSEDCL) ▶
PF
Rs/kVA/mo
Auto-fills from the category/FY schedule when a category is selected; edit to override. Billed on the demand-table peak.
%
% banked
Duty per MH Electricity Duty Act 2016 (industry 9.3% · commercial 21%), auto by category. Banking 8% of energy banked per MSEDCL Circular 346.
The same duty rate also applies on the RE supply, on its total variable cost (RE tariff + transmission + wheeling).
Open access network charges
Rs/kWh
%
Rs/kWh
%
Transmission: MSETCL MYT Rs/kVAh at PF 0.98 (order §5.6.5), losses per MERC Case 217/2024, both FY-keyed. Wheeling applies only when the consumer sits on the MSEDCL 33/11 kV or LT network (MERC ruling); losses HT 7.5% / LT 12%, in kind, in series with transmission.
Time-of-day adjustments
PeriodAdjustment (%)Effective
Peak hours
17:00 – 24:00
—
₹/kWh
Solar rebate · Apr–Sep
09:00 – 17:00
—
₹/kWh
Solar rebate · Oct–Mar
09:00 – 17:00
—
₹/kWh
Base energy, wheeling & demand charges per category and FY; ToD per Review Order Case 75 of 2025 Table 7 — peak +25% for HT/LT Industrial & Commercial (+20% others), solar rebates step to −20%/−30% from FY2027-28, night rebate removed. Adjustments in % of base energy (negative = rebate); manual edits stick.
Solar CAPEX ▶
Cr/MWp
%
Cr/MWp
%
DC/AC
Sets solar AC capacity (MWp ÷ ratio) — drives the MH BESS policy floor and the evacuation-MW basis for common infra.
%/yr
Wind CAPEX ▶
Cr/MW
%
Cr/MW
%
BESS CAPEX ▶
$/kWh
%
%
%
$/kWh
$/kWh
$/kWh
Rs/$
Battery technical ▶
%
%
%
% inst
hrs
2-hr doubles power vs 4-hr at the same MWh. If you model 2-hr, also raise the BESS inverter $/kWh (~2×) — PCS is sized per kW.
Battery degradation schedule (25-yr) ▾
Usable capacity as a fraction of year-1 (Y1 = 1.000). Drives the 25-yr savings curve.
Common infra CAPEX ▶
Cr/MW
Cr/MW
km
Cr/km
Cr/MW
Hard CAPEX — attracts soft costs, contingency, financing and IDC. Per-MW items are sized on evacuation capacity (solar AC + wind); the line is km × Cr/km.
Other CAPEX ▶
%
%
%
Land assumptions ▶
ac/MWp
ac/MW
L/ac
Rs/ac/yr
%
yrs
Rs/ac
O&M ▶
L/MWp
% rev
L/MW
yrs
L/MWh
yrs
kWh/MWh/d
Construction & CAPEX phasing ▶
Construction period: 24 months. CAPEX drawn per the schedule below; IDC accrues on drawn debt, so front-loading raises IDC.
Financing ▶
% of CAPEX/yr
% of equity
Group-captive equity is the consumer's slice: drawn at COD, returned at face value at PPA end (interest-free). It lifts the developer IRR above the SPV IRR.
%
%
%
%
%
days
Debt structuring
years
years
Even = equal principal each year after the moratorium. Choose Custom to enter a % for each operating year (need not sum to 100 — it is normalised).
Sizing override ▶
Overrides the solved sizes to test a configuration. Live — savings, losses and the financial model update without re-solving. The developer tariff is not re-goal-seeked; use Recalculate to re-solve.
Tariff override ▶
Steps of ₹0.05. Updates results live; Recalculate refills the solved tariff.
Battery augmentation ▶
yrs
% initial
Events run on this cadence across the tenor (first at one interval after COD). % of the initially solved BESS capacity. Feeds developer CFADS and the 25-yr savings curve.
Inputs template (Excel) ▶
Download, fill in Excel, upload. Profiles are uploaded separately.
Search precision ▶
Set inputs, then run to size.
Set your target IRR and demand, then run the decision engine.
Run the engine to see customer savings, the blended tariff build-up, losses and the 25-year curve.
Customer headline▾
Blended tariff
₹—/kWh
Grid-only baseline
₹—/kWh
Year-1 savings
₹—Cr
RE penetration
—%
Blended tariff build-up▾
Component
Grid
RE (open access)
Losses & charges (year 1)▾
Banking losses (lapsed)
—
MWh
Transmission losses
—
MWh
Wheeling losses
—
MWh
Contract-demand charges
—
₹ L/yr
25-year savings▾
Annual savings & cumulative (₹ Cr)
Op yr
FY
Savings (₹Cr)
Cumulative
Usable BESS (MWh)
Run the engine. The financial model shows developer returns at the solved tariff, live-editable via the tariff override.
Developer returns▾
Project IRR
—
%
Developer equity IRR
—
% · SPV —%
Min / Avg DSCR
—
x
Returns visualised▾
Profit & loss (INR Cr)
DSCR by year (1.0x floor)
EBITDA & PAT margin (%)
Debt outstanding & leverage
CAPEX & tariff▾
RE tariff (from override)
—
Total CAPEX
—
of which IDC
—
P&L & DSCR by year▾
Yr
Revenue
EBITDA
Interest
PAT
DSCR
A dense sweep of the full Solar × Wind × BESS space at your current inputs. Every feasible point is priced to the target IRR; colour is the customer blended tariff. The green diamond is the solver's optimum — the same sizing shown above, priced on the same engine, so the two can never disagree. Resolution controls how densely the surface is drawn (and how long it takes); it does not change the answer. Wind is always stepped at the solver's 2.5 MW lattice. Heavier compute: ~100 s at 12/axis with wind on.
Search mesh granularity
Auto resolution (points per axis)
Indicative-day dispatch for the solved (or overridden) configuration. Each curve is the hour-of-day average across all 365 days — e.g. the value at 18:00 is the mean across every evening of the year. Hours on the x-axis, average MW on the y-axis.
Run the engine (or set a sizing) to see the dispatch profile.
Supply meets demand — hour by hour
Each column is an hour. Above the line = renewable supply by source; below the line = the customer's demand, with the ungreened part drawn as grid. Where they meet, demand is fully served. Hover a column for the exact split.
1 · Renewable generation — solar & wind
2 · Developer supply to customer (post-battery)
3 · Battery charge & discharge
4 · Consumption from DISCOM (grid)
Demand matrix — 24 h × 12 months (MW)
Fill all:Paste CSV/TSV anywhere in the grid to bulk-fill.